Phone UK  (+44) 028 92441175
Flag IRL  (+353) 01 5256711
Email  
By admin | Published: December 10, 2011

Case Study – Primark Gelsenkirchen Germany

Project Details

  • Client: Primark
  • Main Contractor: John Sisk & Son Ltd
  • Specialist Contractor: Larsen Contracts Ltd
  • Application: Concrete Repair, Resin Flooring
  • Market: Retail

Primark have recently opened its new retail outlet in Gelsenkirchen near Dusseldorf ,Germany. The leading high street retailer has 191 stores throughout the UK, Ireland, Portugal, Germany and the Netherlands. John Sisk & Son Ltd were appointed as main contractor for the fast track refurbishment project with the outlet scheduled to open ahead of the Christmas trading period. The original building was constructed of reinforced concrete in two phases. Unfortunately after the internal demolition contract was underway it was discovered that the concrete in the older part of the building had carbonated to the depth of the steel reinforcement where low cover was also identified. This had allowed the steel to corrode, with subsequent cracking and spalling of the concrete elements. Larsen were invited to meet on site and inspect the works and draw up a technical proposal and programme. The ambitious construction programme required maximum commitment from all trades as time for structural concrete repair had not been originally anticipated.

Having studied the detailed site programme, Larsen mobilised with a large team of experienced operatives and began the mechanical demolition works. When sufficient reinstatement works were ready, the team split into two operations and a repair squad fell back and began the blast cleaning of the reinforcement and the installation of the Remmers Betofix repair mortar. This unique mortar technology allows the repair to be re-profiled quickly with deep fast drying layers without compromising the quality of works. This in turn allowed the other trades to closely follow behind and regain the lost time due to the unforeseen element of work. The repair work was completed ten days ahead of schedule.

[ssba]