Project Details
- Client: Royal Dublin Society
- Consulting Engineer: Keith Loscher
- Principal Contractor: Larsen Contracts
- Scope of Work: Survey and inspection and repair of the Concrete structures at the RDS including preparation of existing concrete structures, concrete repair and application of protective coatings
- Market: Sports /Leisure
Larsen Contracts were appointed as main contractor for the concrete inspection and testing of the Anglesea Stand at the RDS Dublin Home of Leinster Rugby.
The entire stand was visually inspected, hammer tested, and concrete sampling to access carbonation depths, chlorides and cement contents., Having completed the inspection we tendered for the refurbishment works which involved Demolition, Grit blasting and Flowable and hand placed repairs. The works were scheduled over 12 weeks on a live site, The works were accessed via fixed scaffolding and Cherry picker, at all times the stadium remained open with regular preparation and ongoing maintenance of the ground between Heineken Cup Matches. The project was completed two weeks ahead of programme and on budget.